Water Hook-Up Charges

WATER HOOK-UP MAIN TO METER SERVICE LATERAL INCLUDING METER

METER SIZE CHARGE
5/8” –  1” $  6,505
1 1/2” – 2” $  9,831
Above 2” Job Cost Estimate

 

WATER METER INSTALLATION ONLY

METER SIZE CHARGE
5/8” – 3/4” $  319
1” $  391
1 1/2” $  814
2” $  747
Above 2” Job Cost Estimate

 

WATER SYSTEM DEVELOPMENT CHARGE RESIDENTIAL DWELLINGS

METER SIZE SDC
5/8” -3/4” $  3,694
1” $  5,910

 

WATER SYSTEM DEVELOPMENT CHARGE NON RESIDENTIAL GENERAL SERVICE

METER SIZE SDC
5/8” -3/4” $  4,063
1” $  8,496
1 1/2” $  14,407
2” $  34,724
3” $  51,347
4” $  75,358

 

WATER SYSTEM DEVELOPMENT CHARGE IRRIGATION

METER SIZE SDC
5/8”- 3/4” $  5,910
1” $  20,686
1 1/2” $  19,578
2” $  30,291
3” $  51,347

 

WATER SYSTEM DEVELOPMENT CHARGE MULTI-FAMILY DWELLING

$ 2,586

 

WATER SYSTEM DEVELOPMENT CHARGE QUALIFYING SMALL-LOT PUD DWELLING UNIT

$ 2,586