2.0MG Reservoir Improvements

PROJECT NAME–2.0MG Reservoir Improvements

  • Marion Construction Company has been awarded the contract
  • Refurbishment substantially complete. Tank to be painted Spring of 2013.
SCHEDULE:
  • Mobilization: August 28, 2012
  • Demolition: August 31, – September 4, 2012
  • Excavation: August 31, – November 2, 2012
  • Concrete Work: November 11, through November 21, 2012
  • Prestress Tank: September 17, October 10, 2012
  • Re-Coat Tank: October 11, – October 24, 2012
  • Electrical: Ongoing throughout project duration
  • Generator Enclosure: October 8, – October 15, 2012
  • Testing: November 6, – December 3, 2012
  • Completion: End of December 2012
  • Painting delayed until June 2013, weather permitting

DOWNLOADS:

Refurbishment to include:

  • Hydro-blasting & surface preparation (approx 2-3 days) this step will be the loudest of the work to be done but should be done relatively quickly
  • Circumferential pre-stressing
  • Shotcrete application
  • Installing a 300kW generator for emergency power
  • Maintenance and repairs to the concrete tank